Cost Performance Index

Ratio of budgeted cost to actual costs (BCWP / ACWP). Often used to predict the amount of a possible cost overrun or under run using the following formula: BAC CPI = EAC. 


CPI

Cost Performance Index

Ratio of budgeted cost to actual costs (BCWP / ACWP). Often used to predict the amount of a possible cost overrun or under run using the following formula: BAC CPI = EAC. 