Lag

Modification of a logical relationship in a schedule such that there is a delay in the successor task. For example, in a finish-to-start dependency with 5-day lag, the successor activity cannot start until 5 days after the predecessor has finished. 


Lag

Modification of a logical relationship in a schedule such that there is a delay in the successor task. For example, in a finish-to-start dependency with 5-day lag, the successor activity cannot start until 5 days after the predecessor has finished. 