Critical Path

Generally, but not always, the sequence of schedule activitiesthat determines the duration of the project. Generally, it is the longest path through the project. However, a critical path can end, as an example, on a schedule milestone that is in the middle of the project schedule and that has a finish-no-later-than imposed date schedule constraint.


Critical Path

Generally, but not always, the sequence of schedule activitiesthat determines the duration of the project. Generally, it is the longest path through the project. However, a critical path can end, as an example, on a schedule milestone that is in the middle of the project schedule and that has a finish-no-later-than imposed date schedule constraint.